New Construction
Construction began on September 13, 2004.
The
building would grow to be 14,400 square feet, over three times the size
of the old station.1.jpg)
Pouring the footings, September 27, 2004.
Backfilling
the foundation, October 5, 2004.
Pouring
the office area floors, October 19, 2004.
Steel
frame erection begins, October 22, 2004.
October
25, 2004: the steel frame is done.
The
outside walls are all framed, December 23, 2004.
Inside wall framing. January 4, 2005.
Installing
the boiler for in-floor heat on the apparatus floor. February 2,
2005.
District
Trustee Treasurer Pete Wassmann inspects cabinets and counter top in the
EMS Storeroom. February 25, 2005.
Floor
tiling begins, March 3, 2005.
April
4, 2005: Masonry work begins.
April 18, 2005: The brick work is all done.
May 5, 2005: Paving begins.
May
13, 2005: Moving Day!
First rig in....


May 13, 2005
All moved in. |