New Construction

Construction began on September 13, 2004.  The building would grow to be 14,400 square feet, over three times the size of the old station.

 

 

 

 

 

 

 

 

 

 

Pouring the footings, September 27, 2004.

 

 

 

 

 

 

 

 

 

 

Backfilling the foundation, October 5, 2004.

 

 

 

 

 

 

 

 

 

 

 

Pouring the office area floors, October 19, 2004.

 

 

 

 

 

 

 

 

 

Steel frame erection begins, October 22, 2004.

 

 

 

 

 

 

 

 

 

 

October 25, 2004: the steel frame is done.

 

 

 

 

 

 

 

 

 

  

The outside walls are all framed, December 23, 2004.

 

 

 

 

 

 

 

 

 

 

Inside wall framing.  January 4, 2005.

 

  

Installing the boiler for in-floor heat on the apparatus floor.  February 2, 2005.

 

 

 

 

 

 

   

District Trustee Treasurer Pete Wassmann inspects cabinets and counter top in the EMS Storeroom.  February 25, 2005.

 

 

 

 

 

 

  

Floor tiling begins, March 3, 2005.

 

 

 

 

 

 

 

  

  

April 4, 2005: Masonry work begins.

 

 

 

 

 

 

 

 

 

 

April 18, 2005: The brick work is all done.

 

 

 

 

 

 

 

 

 

 

May 5, 2005: Paving begins.

 

 

 

 

 

 

 

 

 

May 13, 2005: Moving Day!

 

 

 

 

 

 

 

 

 

 

First rig in....

 

 

 

 

 

 

 

 

 

 

 

 

 

May 13, 2005

All moved in.